Concrete truck load pricing breaks into two parts: the concrete itself and the delivery
A concrete truck load typically costs between $150 and $250 per cubic yard for the concrete, plus a delivery fee that ranges from $60 to $100 per load in most markets. A standard ready-mix truck holds 8 to 10 cubic yards, so a full load of concrete alone runs $1,200 to $2,500 before delivery. The total bill for a single truck arrival usually lands between $1,300 and $2,600, depending on your location, the concrete mix you order, and how far the truck travels from the plant.
What you actually pay depends on four concrete factors: the type of mix (standard concrete costs less than air-entrained or fiber-reinforced), the strength rating in PSI (pounds per square inch), the distance from the ready-mix plant to your site, and whether you need the truck to wait while you pour. Most residential jobs use standard concrete at 3,000 to 4,000 PSI, which sits at the lower end of the price range.
Key Takeaways
- Concrete costs $150 to $250 per cubic yard, and a full truck holds 8 to 10 cubic yards, so expect $1,200 to $2,500 for the material alone.
- Delivery fees of $60 to $100 per load explore on top of the concrete price, and some plants charge extra if the truck must wait more than 30 minutes.
- Distance from the ready-mix plant to your site is the single largest variable—jobs more than 20 miles away often face surcharges or higher base prices.
- Ordering less than a full truck load (partial loads) costs significantly more per cubic yard and may not be available from all plants.
- Concrete strength, air entrainment for freeze-thaw protection, and fiber reinforcement all add to the per-yard cost.
How ready-mix plants price concrete by the cubic yard
Ready-mix concrete plants charge by volume, measured in cubic yards. One cubic yard equals 27 cubic feet and covers about 81 square feet at 4 inches thick. The base price per yard covers the cement, sand, gravel, water, and standard mixing. Most plants publish a price list, but the actual quote you receive depends on what you order and when.
Standard concrete for driveways, patios, and foundations typically costs $150 to $200 per cubic yard in rural areas and $180 to $250 in urban markets where land and plant operations are more expensive. Air-entrained concrete, which contains tiny air bubbles to resist freeze-thaw damage in cold climates, adds $10 to $20 per yard. Fiber-reinforced concrete, which uses plastic or steel fibers instead of rebar for crack control, adds $15 to $30 per yard. High-strength concrete rated at 4,500 PSI or higher costs $20 to $40 more per yard than standard 3,000 PSI mix.
Delivery fees and distance surcharges
The delivery fee covers the truck, driver, and fuel to bring concrete from the plant to your site. Most plants charge a flat delivery fee of $60 to $100 per load, regardless of how many yards you order (as long as it fits in one truck). Some plants build the delivery fee into the per-yard price instead of charging it separately, so always ask whether the quote includes delivery.
Distance from the plant is where costs climb. If your job is within 5 to 10 miles of the plant, you pay the standard delivery fee. Beyond 10 miles, many plants add a mileage surcharge of $1 to $3 per mile for each mile over the threshold. A job 25 miles away might add $30 to $45 to the delivery cost. Some plants in rural areas have a minimum delivery distance or will not service jobs beyond a certain radius at all, so confirm the plant will reach your address before you get a quote.
Partial loads and minimum order requirements
If you need fewer than 4 cubic yards, you are ordering a partial load. Most ready-mix plants charge a premium for partial loads because they cannot fill the truck to capacity and still serve other customers efficiently. A partial load might cost $200 to $300 per cubic yard instead of $150 to $200, or the plant may charge a flat fee of $200 to $400 plus the per-yard rate. Some plants do not offer partial loads at all and require a minimum order of 4 to 5 cubic yards.
If you need only 2 or 3 cubic yards, your options are to order from a plant that accepts small loads (usually at a premium), to rent a concrete mixer and buy bags of concrete mix from a building supply store (more labor-intensive but sometimes cheaper for very small jobs), or to wait and combine your order with another project. Bagged concrete costs $3 to $5 per 60-pound bag and requires hand mixing, so the math only works for jobs under 1 cubic yard.
Wait time charges and pump truck costs
Ready-mix trucks are charged by the hour once they arrive at your site. Most plants include 30 minutes of wait time in the delivery fee. If you are not ready to pour when the truck arrives, or if the pour takes longer than 30 minutes, you pay a wait charge of $50 to $100 per 15-minute increment. This is why contractors emphasize having your site prepared, your forms set, and your crew ready before the truck shows up.
If your site does not allow the truck to back up to the pour location—because of narrow access, overhead obstacles, or soft ground—you need a pump truck. A concrete pump truck costs $300 to $600 per day or $100 to $200 per hour, depending on the pump size and your location. The pump extends a boom or hose to reach the concrete into tight spaces, basements, or upper floors. For small residential jobs, this cost often exceeds the concrete cost itself, so it is worth exploring whether you can widen access or relocate the pour before committing to a pump.
Regional price variation and seasonal timing
Concrete prices vary significantly by region. Urban areas in the Northeast and West Coast typically run $200 to $250 per cubic yard, while rural areas in the Midwest and South may be $140 to $180. The difference reflects local labor costs, fuel prices, and competition among ready-mix plants. Areas with only one or two plants nearby often have higher prices because there is less price competition.
Seasonal demand also moves prices. Spring and summer are peak concrete season, and some plants raise prices or add surcharges during these months. Winter pours in cold climates cost more because the concrete requires additives to cure properly in freezing temperatures, and fewer plants operate at full capacity. If your project timeline is flexible, ordering in fall or early spring can save 10 to 15 percent compared to peak summer rates.
Getting an accurate quote from a ready-mix plant
When you call a ready-mix plant for a quote, have this information ready: the total cubic yards you need, the concrete strength (PSI) and type (standard, air-entrained, or fiber-reinforced), your site address, and the date you want delivery. The plant will calculate the per-yard cost, multiply by your yardage, add the delivery fee and any distance surcharge, and give you a total. Ask whether the quote includes wait time and whether there are additional charges if the truck must wait beyond 30 minutes.
Get quotes from at least two plants, because prices vary and one plant may offer better service or shorter lead times for your delivery date. Ask each plant about their minimum order, whether they charge for partial loads, and whether they can deliver on your preferred date. Some plants book up weeks in advance during peak season, so plan ahead if you are pouring in spring or summer.
Frequently Asked Questions
How much does a full concrete truck load weigh?
A full truck load of 10 cubic yards weighs approximately 40 to 45 tons (80,000 to 90,000 pounds), including the truck itself. Make sure your driveway or site can support this weight, or the truck may sink or damage the surface. Some contractors place steel plates or boards under the truck wheels to distribute the weight.
Can I order concrete for delivery tomorrow?
Most ready-mix plants require 24 to 48 hours' notice for delivery, though some plants in competitive markets may accommodate rush orders for an extra fee of $50 to $150. Call early in the day to ask about same-day or next-day availability. Weekend and holiday deliveries usually cost more or are not available.
What happens if I do not use all the concrete in the truck?
You pay for the full load regardless of how much you pour. Leftover concrete hardens in the truck and is expensive to remove, so contractors plan carefully to use as much as possible. Some plants accept return of unused concrete for a credit, but this is rare and usually requires advance agreement.
Is there a difference between ready-mix and bagged concrete?
Ready-mix is delivered wet and ready to pour; bagged concrete is dry and requires hand mixing with water. Ready-mix is faster and stronger for large jobs, but bagged concrete is cheaper for small projects under 1 cubic yard and does not require a truck. For anything over 2 cubic yards, ready-mix is usually the better value.
Do I need to pay for concrete if weather prevents the pour?
Yes, you typically pay for the concrete even if weather delays the pour, because the truck is reserved and the concrete is mixed. Some plants allow you to reschedule delivery within a few days at no extra charge, but canceling usually means losing the full payment or paying a cancellation fee. Always check the plant's cancellation policy before ordering.